What it is about
Clause 6.1 sits at the start of planning. Before an organisation sets objectives and defines its processes, it should know what could go wrong along the way and where something better might open up. The standards call these risks and opportunities; in both cases they mean the same uncertainty, once with an adverse effect and once with a beneficial one.
What is asked for is not a complete list of every conceivable hazard. The point is what actually affects the intended results of the management system: satisfied customers, compliance obligations that are met, information that is protected. The sources for this already exist, namely the issues from 4.1 context and the expectations from 4.2 interested parties.
Determining leads to acting: for every risk that needs to be addressed and every opportunity that is to be pursued, the organisation plans actions, integrates them into its processes and later checks whether they have worked. It is exactly this chain, from the source through to effectiveness, that the audit follows.
What the auditor checks
“What are your three most important risks, and why those in particular?”
Whether the answer comes from your own operations or from a template. People who know their risks name them without looking at the list and can say where they come from.
“How do the context and your customers’ expectations find their way into this list?”
The link to 4.1 and 4.2. An issue from the context with no consequence in the risk assessment stands out just as much as a risk with no recognisable origin.
“Show me an action from last year. How did you know it was working?”
Whether effectiveness was actually evaluated, with a date and a result, and whether someone was responsible for it. “Done” says nothing yet about the effect.
“Which opportunity have you deliberately pursued?”
Whether opportunities are considered in their own right or only sit as a positive leftover column in the risk register. The 2026 edition of ISO 9001 separates the two more clearly.
“When did you last adjust the assessment, and what prompted it?”
Whether the assessment is alive: new products, sites, suppliers or incidents should leave traces in it. A register still dated to the initial certification tells the opposite story.
“Which risk affects your area the most?”
Put not to the quality management representative but to the person responsible for an area, for example in production or purchasing. The register is lived when their answer matches what it says without them having to look it up. Anyone who first has to search or names something entirely different knows the register only by hearsay.
Which evidence convinces
An overview of risks and opportunities with assessment, date and owners
It shows at a glance what has been determined and how important it is. Whether it is a spreadsheet or in software makes no difference; it has to be traceable.
A defined assessment scale
Two people should rate the same risk in a similar way. Without defined scales and thresholds, an assessment can hardly be checked in the audit.
Actions with owners, deadlines and status
An action without a name and a date is an intention. With both, the audit can follow what became of it.
The documented evaluation of effectiveness
It closes the chain. The strongest evidence is a figure before and after, such as the scrap rate or the failure rate. A result like “not yet sufficient, action extended” is also convincing, because it shows that someone looked. A register with 80 rows in which every action reads “done”, on the other hand, only looks tidy.
Risks and opportunities as a topic of the management review
This shows that top management knows the situation and has decided on resources.
Typical nonconformities
The list comes from a template
Fire, cyber attack, skills shortage: generic risks with no connection to your own operations and no origin in the context or the interested parties. This becomes clear quickly in conversation, because nobody can explain why an entry is there.
Actions without a check of their effect
Actions are planned and ticked off, but nobody has evaluated whether they changed anything. This is the most common finding in this clause, because the last step is the easiest one to let slide in day-to-day work. If the evaluation is missing in a single case, it is usually an observation; if it is missing throughout, a minor nonconformity.
Actions are left lying
A finding from practice: actions on highly rated risks have been overdue for more than a year, and nobody has pointed this out to top management. As a rule, this is a minor nonconformity. If it is still unchanged at the follow-up audit, it becomes a major nonconformity.
The assessment is frozen
Unchanged since the initial certification, even though a site was added, an important supplier changed or an incident occurred.
Opportunities are missing
The register only knows risks, or opportunities appear in it as a counterpart without a decision of their own on whether and how they will be pursued.
Residual risk without approval (ISO 27001)
The treatment plan is in place, but the risk owners have not approved it and have not explicitly accepted the remaining risks. Or the Statement of Applicability does not match the controls in the plan.
Differences by standard
ISO 9001ISO 9001
ISO 9001 does not prescribe a formal method and does not require a documented risk management process. The route is open, traceability is not: if you determine risks, plan actions and evaluate their effect, you must be able to show it. The 2026 edition separates risks and opportunities more clearly and relates the actions to the results of the entire quality management system, not just to the products. More on this in the article on the 2026 edition under “Further reading and viewing”.
ISO 14001ISO 14001
In ISO 14001, 6.1 is structured more broadly: alongside risks and opportunities come the environmental aspects and their evaluation, and the compliance obligations, in other words the legal register. A risk in environmental management is therefore often the consequence of a significant environmental aspect or of an obligation that is not reliably met. Potential emergency situations are explicitly included, and the results are to be documented.
ISO 27001ISO/IEC 27001
ISO/IEC 27001 demands the most precise route: criteria for assessing and accepting risks, an approach that produces repeatable results, named risk owners, then treatment with a comparison against Annex A, the Statement of Applicability and a risk treatment plan. Finally, the risk owners approve the plan and accept the residual risks. The assessment is carried out at planned intervals and when significant changes occur (clauses 8.2 and 8.3).
How IMScollect covers it
In IMScollect, risks and opportunities sit in one register, shared across all standards, with each entry showing the standard it concerns. Assessment is by likelihood and impact; the heat map shows the situation before and after the actions.
For each risk you choose one of the four treatment options, plan actions with owners and deadlines, and every action becomes a task. The residual risk gets an owner who accepts it. A risk can be created directly from an interested party or an incident, so that its origin stays visible. The AI advisor Conni suggests assessments and suitable actions; only what you approve is adopted.
Frequently asked questions
Does ISO 9001 require a risk register?▾
ISO 9001 requires neither a register nor a particular method. In the audit, however, you must be able to show which risks and opportunities you have determined, what you are doing about them and how you evaluate the effect. A register is the usual and simplest way to do this.
Is one shared register enough for ISO 9001, 14001 and 27001?▾
Yes. A list with a column for the standard concerned is enough. For ISO 27001 it must also carry everything that standard requires: risk owners, risk acceptance criteria, a risk treatment plan and the link to the Statement of Applicability.
How often does the risk assessment have to be updated?▾
The standards do not set a fixed interval; ISO 27001 requires the assessment at planned intervals and when significant changes occur. A proven approach is a review at least once a year ahead of the management review, and additionally whenever something changes: new products, sites, suppliers or an incident.
What is the difference between a risk and an opportunity?▾
Both arise from the same uncertainty. A risk can prevent an intended result, an opportunity can improve it. A looming supply shortage is a risk; a regular customer offering a long-term framework agreement is an opportunity.